How are we doing?
The roof to the building is all but complete with the guttering commencing the week of the 24th March. Windows have been installed making the building water tight, this means the mechanical and electrical works and internal finishing can commence. The external render is underway and due to be painted.
Current works:underfloor heating pipes have been laid which enables the floor screeding to commence. Second fix mechanical and electrical works including containment and chasing and cabling has started. Plasterboarding is starting internally.